103. The promoter must notify the Minister when a project is withdrawn from an aggregation and continued, within 30 days of the withdrawal. The notice submitted must update the information contained in the project notice provided for in section 78 and in the summary of the aggregation provided for in section 101.
2022-11-17M.O. 2022-11-17, s. 103.